LaSalle RO Quiz

20 Random Questions, RO only, all Exam Years

 

Results

#1. LGA-RT-101; RPV Depressurization Using RWCU Blowdown is in progress and theMain Condenser is NOT available to accept RWCU flow.For the given conditions; LGA-RT-101 provides an ALARA warning for abnormally highairborne radiation levels in the . . .

#2. A reactor startup following a 21 day refueling outage is in progress on Unit 2: The NSO determines the reactor is critical and stops rod withdrawal. Reactor power continues to rise with no rod motion. One hour later; reactor power turns and begins to lower.In accordance with LGP 1-1 Attachment L; Precautions to Be Used Before; During; and After Pulling Critical (1) Why did reactor power start lowering? (2) Which of the following would indicate the reactor has returned to subcritical?

#3. The Unit 1 reactor is shutdown with head installed and the following conditions: – Coolant temperature is 170F – ‘B’ train residual heat removal is in shutdown cooling operation at 7000 gpm – both recirculation pumps out of service – reactor water level is being maintained at +50 inches on the Shutdown RangeIf an inadvertent PCIS Group 6 isolation occurs and the isolation signal can NOT be cleared; inorder to minimize thermal stratification of the bottom reactor vessel head AND enhance RPVmoderator temperature monitoring; the operators would . . .

#4. Given the following: A reactor startup is in progress NO control rods have been withdrawn Initial SRM count rates are: SRM A 30 SRM B 35 SRM C 50 SRM D 45Which of the following is the requirement IAW LGP-1-1 “Unit Startup” to STARTsingle notch withdrawal of control rods?

#5. The Unit 1 reactor core is being loaded with the following conditions in place: – All SRMs are fully inserted – All control rods are fully inserted – There are at least 6 fuel assemblies adjacent to each SRM – There are more than 10 fuel assemblies loaded in each quadrant. Determine if loading fuel at location 15-18 is allowed; and if the requirement for operable SRMs is met.

#6. Due to a security event Both Units are shutdown with the following conditions: Both Unit 1 and 2 SATs are NOT available. Both Unit 1 and 2 Division 1 and 2 DGs are NOT available.Which of the following is the Preferred action to be taken to mitigate an off-siterelease?

#7. To provide an additional margin of safety; the APRM Flow Biased Simulated ThermalPower Upscale Trip and alarm setpoints are automatically adjusted in proportion to (1) flow rate signals. These signals are passed through a (2) valuegate to ensure conservatism is added to the flow biased trip circuits.

#8. During a casualty; an NSO opened an SRV to control RPV pressure. The SRV was closed andmanually opened again 15 seconds later.Which one of the following describes the potential adverse consequences of this action?

#9. Which of the following describes the minimum and maximum level indications that can be monitored from the Remote Shutdown Panel? Minimum: _________(1)________ Maximum: _________(2)________

#10. Unit 1 was operating at 100% reactor thermal power with SRV 1B21-F013U; leaking steam pastits seat. The leakage caused the suppression pool to heatup. Under these circumstances;initiating suppression pool cooling would be necessary to prevent __________ during accidentconditions.

#11. What are the Operational implications of the 0 DG room temperature reaching 109 F and the 0 DG is in operation. When the 0 DG is secured …

#12. Unit 1 has experienced a LOCA. LGA-004 has been performed based on the Pressure Suppression Pressure limit being exceeded. Containment Pressure is at 52 psig and increasing. LGA-VQ-02; Emergency Containment Vent has been directed. Actions during the performance of this procedure should include &

#13. Given the following initial plant information: Unit-1 is in a refueling outage. Unit-1 UAT is a qualified off-site source. Bus 13 is de-energized. Unit-2 is in Mode 2 with a start-up in progress.Given this initial lineup; which one of the following combinations of failures wouldresult in a loss of all Off-Site AC power to both units?

#14. Unit 2 RCIC is in a normal standby lineup. Leaking valves cause Suppression Pool Level to increase such that High Suppression Pool Water Level alarms are received on the 2H13-P601 panel. Which one of the following describes the response of the RCIC system to this condition?

#15. The Off-Gas system was in operation with flow bypassing the charcoal adsorber trains(Charcoal Adsorber Train mode switch was in AUTO). Power was subsequently lost to24/48 VDC Distribution Panel 1A. The Off-Gas system flow-path will . . .

#16. A LOCA has occurred in the Drywell on Unit 1: Drywell pressure is 5 psig. Drywell temperature is 340°F. Suppression Pool level is + 10 feet. What is the operational impact; if any; of initiating Drywell Sprays?

#17. Unit 1 was at full power operation with RCIC operating for a quarterly surveillance test. TheUnit 1 control room NSO received a report from equipment operators that the RCIC room wasfilled with steam. The NSO observed RCIC area temperatures and noted the following: – RCIC Equipment Area ambient temperature was 195F and increasing – RCIC Area Vent Differential temperature was 103F and increasing – Annunciator 1H13-P601-D411; “Div I RCIC Equip Area Diff/Area Temp Hi;” was alarming – Division II; RCIC Primary Containment Isolation System had NOT actuatedAssuming no operator actions were initiated; the RCIC Turbine Steam Supply _____(1)_____automatically close(s) AND operator actions need be taken to _____(2)_____.

#18. Both Units are operating at 100% power: Station Air Compressors 2SA01C and 0SA01C are running in a normal lineup. Unit 2 Turbine Building Closed Cooling Water (TBCCW) flow is lost in the Turbine Building. How will the Station Air compressors respond if TBCCW flow is NOT restored in the Unit 2 Turbine Building?

#19. A LOCA has occurred on Unit 2 – Drywell pressure is 2.1 psig – Reactor water level is -25 inches and stable – The HPCS injection valve has been manually closed – The HPCS Pump has been overridden to STOP Which of the following describes the response of the HPCS system if Off-site power is lost and the ESF buses are re-energized by their respective Diesel Generators? The HPCS system will. ..

#20. Unit 1 is in Mode 4: Reactor Coolant temperature is 150 F Alternate shutdown cooling is in operation with heat removal provided by the reactor water cleanup system 2 RT filter demineralizers are in service The B RWCU Non-Regenerative Heat Exchanger is in use to maintain vessel temperature, with the local D/P gauge 1PDI-WR028, reading of 10.0 psidTwo minutes later: The local RBCCW D/P gauge 1PDI-WR028, reads 2 psid The WR head tank level is steadyWhat is the significance in the change of this D/P reading and the consequence of this change?

Previous
Finish