LaSalle SRO Quiz

20 Random Questions, SRO only, all Exam Years

 

Results

#1. The reactor vessel water level Safety Limit (SL) ensures that adequate core coolingcapability is maintained during (1) of reactor operation. Establishment ofEmergency Core Cooling System (2) provides margin such that the SL willNOT be reached or exceeded.

#2. Unit-1 was at full power when it was determined that the Suppression Pool Wide Range levelinstruments for both divisions were improperly calibrated. The system engineer determined thatactual Suppression Pool level is 700 feet 2.5 inches.For this condition; the MOST limiting action according to the Technical Specifications can befound in …

#3. Unit 2 is operating near full power when instrument maintenance technicians discovered that three turbine stop valve closure channels that input to RPS are inoperable. PROVIDE T.S. 3.3. 1. Which of the following actions is required?

#4. Using the attached reference(s) and given the following: Unit-1 is shutdown Reactor recirculation temperature is 205F Instrument maintenance has completed LIS-LP-108; LPCS PUMP HIGH/LOW DISCHARGE PRESSURE ALARM CALIBRATION. The instrument technician informs the unit supervisor that the 1E21-N005B; LPCS System Discharge Pressure Low Switch; does NOT meet calibration requirements. 1H13-P601-C308; LPCS System Discharge Pressure Low Annunciator; did NOT reset. An operator was dispatched and identified that there was water at the high point vent and local pressure indicated 55 psig. What is the impact on Tech Spec 3.5.1 and 3.5.2?

#5. You are the Unit 1 Unit Supervisor. With Unit 1 operating at rated conditions; a manual scram was inserted due to a sudden drop in condenser vacuum. The Unit 1 NSO transferred the Mode Switch to SHUTDOWN and then reported the following: – Four rods remain FULL OUT. – RPV Level is – 15 inches and rising slowly – Suppression Pool temperature is 106 F and going up slowly Based on the indication below; reactor power is determined to be _______(1)________ and you must provide direction to hold RPV level in the band of ________(2)________; in accordance with the governing LGA.

#6. Unit 1 has scrammed due to a Loss of Off-Site Power. Both Div 1 and 2 DGs failed to start. HPCS DG tripped 15 minutes into the event. RCIC is maintaining level at -75″.(1) What are the required actions to keep RCIC available for injection after4 hours?(2) What procedure will the Unit Supervisor direct after 4 hours?

#7. Unit 2 is experiencing an ATWS with the following conditions: Reactor water level is 10 inches and is being rapidly lowered. – The Reactor operator reports that APRMs are oscillating between two and sixteen percent. Which of the following actions should be taken?

#8. Given the following Conditions: Reactor Mode Switch is in Shutdown. Average Reactor Coolant Temperature is 205 F. Reactor Vessel Head Closure bolt tensioning will be complete in 2 hours.The Unit is currently in __ (1) and the __ (2) __ must be completed prior to the completion of Reactor Vessel Head closure bolt tensioning.

#9. An unisolable RWCU system leak to the Reactor Building is in progress with the following: – A failure to scram has occurred. – Reactor power is 15%. – RPV water level is being intentionally lowered. – Both RHR pump room water levels are 2 feet. – Only 2 SRVs can be opened and are open. – Reactor pressure is 1080 and slowly rising. – Suppression chamber pressure is 2 psig and steady.(1) Which of the following identifies the MSIV isolations that should be defeated and(2) what is the required pressure control band?

#10. Unit 1 has been operating at rated conditions for an extended period of time. A Loss of Offsite Power results in a Group 1 isolation. RCIC is being used to maintain Reactor water level. Based on the stated conditions; what is the LOWER value of the Reactor Water level band that the CRS should direct the NSO to maintain?

#11. You are reviewing the shift manning schedule and identify that two of the fourReactor Operators (RO) scheduled for the next shift have No-solo Operationrestrictions on their license.What action; if any; is required to be taken regarding shift staffing for the next shift?

#12. Several hours after an automatic initiation during a LOCA; and with the initiationsignal still present; the Unit-1 Standby Gas Treatment Primary Fan trips.After the trip; the Unit-1 Assist NSO observed the following at panel 1PM07J:- SBGT Primary Fan – OFF- SBGT Cooling Fan – OFF- SBGT Heater – OFF- SBGT Flow – 0 scfm- 1VG001; SBGT Inlet Isolation damper – CLOSED- 1¥VG003; SBGT Outlet Isolation damper – OPENThe SBGT train (1) to the Primary Fan trip and the Unit Supervisor shoulddirect the operator to (2) .

#13. The Technical Specification bases for the Main Steam Line Pressure-Low Primary ContainmentIsolation is . . .

#14. Unit 1 is in Run with recirculation loop flow mismatch of 3000 gpm. Which of the following is the MAXIMUM percentage of core flow that is allowed to exist WITHOUT entering a Technical Specification Action statement?

#15. In order to maintain an active Senior Reactor Operator (SRO) License, quarterly, the MINIMUM the License Holder must stand is…

#16. Unit-1 is in Mode 4 with reactor coolant temperature at 190F. The |operating loop of Shutdown Cooling trips and can NOT be restarted. Both Reactor |Recirculation pumps are out of service and Reactor Water Cleanup (RWCU) is isolated. |It has been determined that it will take 2 hours to align and start the standby Shutdown |||Cooling loop.As the Shift Manager you should …

#17. Unit 1 was operating at full power when a loss of feed occurred. All RPV Level 3 and Level 2actuations and isolations functioned as designed except the Standby Gas Treatment systemfailed to start. RCIC subsequently isolated due to a high RCIC room temperature; however;RCIC room temperature is now trending downward. Operators have determined that NO otheractuation or isolations signals currently exist.Select the statement below that correctly describes action(s) required to be directed by the UnitSupervisor in accordance with LGA-002; Secondary Containment Control:

#18. 165 F.The Unit is currently in (1) and the (2) must be completed prior to Reactor Vessel Head closure bolt detensioning.

#19. Unit 2 is in Mode 5. You are the Unit 2 Control Room Supervisor Fuel movements are scheduled to begin; for the first time in the outage; later thisshift. Non-Spiral off-loading is being utilized. 24/48VDC Bus A is de-energized. The Fuel Handling Supervisor has called you to request permission tocommence fuel movements. The only item remaining to be checked is the operability of required nuclearinstrumentation.Based on the given conditions; fuel movements (1) as (2) .NOTE: Technical Specification 3.3.1.2 SRM Instrumentation provided.

#20. Unit 2 is at rated power with the following conditions: – HD tank level increasing. – HD Pump Minimum Flow Valves opening. – HD Pump Forward Valves closing. – LP Heater Emergency Spills Valve opening. Which of the following is responsible for all of the conditions AND which procedure(s) should be implemented?

Previous
Finish